Reference E - Install Schedule

Refer to these Process IDs: DD-9, CD-8, PI-14, PI-15, PI-16.

Optimization of modular components is dependent on efficient integration of modular components within the construction sequencing. The General Contractor and Manufacturer should work together to establish the optimum schedule for installing modular components.

Factors to be considered include:

  • Number of days available or required for installation of units
  • Number of installers to be utilized
  • Whether units will be installed in a single phase or
  • Whether project will be divided in multiple phases

The goal of the install schedule is to provide clarity for what each team member of the install team will be responsible for completing each day. The schedule is coordinated with the install plan that shows the location of each module to be installed.