BP-4
Obtain Manufacturing Certification (if req'd)
  • In many jurisdictions, a Manufacturer is required to become certified in order to provide pre-inspected, "closed" (having concealed piping, connections or components) manufactured components that can be incorporated into site construction without local AHJ inspection.
  • Manufacturing certification generally includes:
    • QA/QC system approval
    • Unit design approval
    • Plant certification
  • The certification process varies in duration.
  • Depending on the jurisdiction, it may take weeks or months to obtain.
  • Manufacturer should begin the certification process as soon as the project location has been identified.